Georgia

Collection Agency Georgia
Collection Agency Georgia

Engineers, Architects and Land Surveyors do not have to file a pre-lien notice. Professional engineers may file a claim within 90 days after completion of the work or furnishing of the services. They must notify the owner by registered or certified mail no later than 2 business days after the claim is filed and notify the superior court in the county in which the lien was filed within 30 days. Georgia Code Title 44 Chapter 14-361.

Disclaimer:Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.